Wettingen postpones the construction of 147 flats once again

The Schartenstrasse development plan is open for public consultation on the Lägere site in Wettingen from 19 November until 18 December 2026. Although the project – comprising 147 rental flats for around 290 people – is thus progressing through the planning process, its completion is now not expected until 2032 following further delays.
3 minutes to read
Share this post

Wettingen postpones the construction of 147 flats once again

The private development plan was drawn up in collaboration with the local council between 2024 and 2026, preliminarily reviewed twice by the canton, and approved by the local council for public consultation in early November 2026. A new residential neighbourhood is to be built on the former market garden site on Schartenstrasse, which covers an area of around 14,600 square metres; however, according to the current timetable, the plan will not become legally binding until the end of 2027.

The plans envisage seven residential buildings, each with three full storeys and an attic storey. The draft scheme comprises 147 rental flats, the majority of which have 2½ to 4½ rooms, plus eight 5½-room flats and one 1½-room studio. In total, the development is designed to accommodate around 290 residents.

The canton did not simply allow the density to proceed
The design plan deviates from the zoning regulations in terms of the number of storeys, building height, floor area ratio, and distances from roads and boundaries. It was precisely this that sparked the years-long delay. In its final preliminary assessment report of October 2026, the cantonal Department of Spatial Development has since given the plans a generally positive assessment and attested to their high quality in terms of design and planning. However, it continues to call for a critical review of the high density.

Furthermore, two issues with a direct impact on the procedure remain unresolved. It must be clarified where balconies and other parts of the building may protrude beyond the specified building areas. In addition, proof must be provided – even at the stage of approving the design plan – that the necessary sightlines for traffic are legally guaranteed.

Public consultation under way, start of construction still some way off
The publicconsultationon the Schartenstrasse design planrunsfrom 19 November to 18 December 2026. Afterwards, the comments will be evaluated, followed by a public display, a municipal council decision and cantonal approval. Only once these steps have been completed without any further obstacles can the project move on to the planning permission phase.

The development is planned to include 149 car parking spaces and 526 cycle parking spaces. The mobility concept allows only limited scope for reducing the number of parking spaces, partly due to the half-hourly bus service to Wettingen station. Also planned are a communal area, commercial premises, a nursery, green roofs and 117 native trees.

The developer expects to receive planning permission in spring 2029. Completion of the residential development is expected by 2032. For Wettingen, this means that whilst a major inner-city regeneration project is once again making visible progress, several more years will be lost in terms of creating additional housing.